Harbourfront Centre Community Square

Toronto, ON

Recreation

Harbourfront Centre's pond and Natrel Rink, for decades one of Toronto's most photographed skating spots, had reached the end of their life. EMC Group Limited provided the civil engineering that turned that site into an all-season Community Square on the central waterfront, designed by MJMA Architecture & Design. The stormwater design had to answer to Lake Ontario: outfall capacity governed by lake levels, a storm outfall whose location, size and condition were confirmed by divers, custom permeable pavement over a below-grade storage reservoir, and an end to the drainage problems the Centre had lived with for years.

Project at a Glance

Location
Harbourfront Centre, 235 Queens Quay West, Toronto, ON
Type
All-season public square on the site of the former pond and Natrel Rink
Owner
Harbourfront Centre
Design
MJMA Architecture & Design
Opened
2024
Status
Completed
Site Photography
Harbourfront Centre Community Square – Crowds on the paved plaza and curved timber benches with Lake Ontario behind
Harbourfront Centre Community Square – People seated on curved timber slat benches around the paved plaza
Harbourfront Centre Community Square – Child running through fog on the plaza behind a timber slat bench
Aerial Photography
Harbourfront Centre Community Square – Drone view of the stage, curved bench edge, tree grove and crowd on the plaza
Harbourfront Centre Community Square – Drone view straight down onto the two-tone paving pattern with crowds and a dance floor
Harbourfront Centre Community Square – Drone view of the paved plaza with visitors, movable seating and a dance floor
Design Site Plan
Harbourfront Centre Community Square – Site plan showing the curvilinear plaza with fog feature, stage, benches, tiered seating, umbrella seating and tree groves beside the Waterfront Trail

Site plan by MJMA Architecture & Design. The curvilinear plaza holds the fog feature at its centre, with the stage, communal benches, tiered seating, umbrella seating and tree groves around its edge and the Waterfront Trail along the harbour. The permeable paving and below-grade storage reservoir engineered by EMC sit beneath the plaza.

Interactive map showing the subject site with property boundary overlay. Click the map to enable scroll zoom.

Subject Site Property Boundaries

From pond and rink to an all-season square

The pond and rink at the heart of Harbourfront Centre's York Quay site were closed in 2023 when repair costs became untenable. MJMA's renewal began with replacing them and grew into a complete rebuild of the public square as a year-round destination: a level plaza of custom precast paving, curvilinear communal benches, a performance stage, tiered seating, tree groves at the east and west edges, movable shade umbrellas, integrated power and lighting for events, and a 617-nozzle fog feature that draws people into the square by day and becomes a canvas for light at night. Temporary winter skating returned to the square in December 2024, so the site again works in every season.

Stormwater at the water's edge

A square built at the lake has no gravity to spare. The outfall that drains the site discharges to Toronto Harbour, so its capacity rises and falls with Lake Ontario, and the stormwater design had to work through the full range of lake levels rather than a fixed outlet. Before any of that could be designed, the outfall itself had to be trusted: EMC brought in divers to verify its location, size and condition under water, so the new system was sized against what was actually there rather than what old drawings suggested.

Custom permeable pavement over a below-grade reservoir

Because the outfall cannot be relied on in every storm and every lake condition, the square stores water where it falls. The plaza's custom precast concrete slabs were designed as a permeable surface, passing runoff through the joints into a below-grade storage reservoir beneath the square. The reservoir holds the storm and releases it to the outfall at a rate the harbour connection can accept, while keeping the plaza surface free of standing water during events. The design also resolved the drainage problems Harbourfront Centre had experienced on the site for years, collecting the flows that previously ponded and giving them a controlled route to the lake.

Engineering beneath a working fog feature

The fog feature spreads across the plaza from hundreds of spray heads set into the paving, and the water that falls out of it has to go somewhere. The permeable surface and reservoir take that water along with rainfall, so the feature can run through a summer day without the square becoming a wet floor. Below the paving, EMC coordinated the storm, water and drainage servicing with the feature's supply lines, the stage and bench footings, the tree grove soils and the electrical distribution that lights the square at night.

Project team

Landscape architecture and design by MJMA Architecture & Design; structural engineering by Blackwell; mechanical and electrical engineering by Smith + Andersen; water feature design by Aqua Plans; branding and graphics by Barnbrook; civil engineering and stormwater management by EMC Group Limited.

Harbourfront Centre Community Square – Visitors walking through the fog feature with the Simcoe WaveDeck and city skyline beyond
Harbourfront Centre Community Square – Walkway through the tree grove at the edge of the square with Lake Ontario beyond
Harbourfront Centre Community Square – Crowds in the fog feature with the harbour, boats and an ice cream truck behind
Harbourfront Centre Community Square – Visitors running through fog beneath the trees at the edge of the plaza